Realized projects

Reduction of dust emission in CHP plant Inowrocław through modernization of electrostatic precipitator of the boiler OP 110 No. 1 and 3

Beneficiary: CIECH Soda Polska S.A. 

Value of eligible expenses according to the financing agreement: 10 400 000 PLN 

Value of financing from Norwegian Financial Mechanism: 3 120 000 PLN

The project: “Reduction of dust emission in CHP plant Inowrocław through modernization of electrostatic precipitator of the boiler OP 110 No. 1 and 3” is subject to financing from the Norwegian Financial Mechanism 2009-2014 under the Programme PL04 “Saving energy and promoting renewable energy sources”. 

The project is realized according to the financing agreement between CIECH Soda Polska S.A. and the Minister of Environment. The grant amount reaches 30 percent of the eligible costs of the project. The main purpose of the project is to improve air quality by reduction of dust emission. 

Approval for financing the project from the Norwegian Financial Mechanism 2009-2014 confirms that its realization will cause a significant environmental effect, contributing to improvement of air quality by substantial reduction of pollution emission. 

Link to the webpage of Norway Grants:

www.norwaygrants.org
eeagrants.org/Who-we-are/Norway-Grants
www.eog.gov.pl/

Project implementation progresses

Electrostatic precipitator of boiler OP 110 No. 1

Delivery of the construction site

2014-01-30

Dismantling works of the electrostatic precipitator of steam boiler OP-110 No. 1

2014-03-03

Completion of assembly of walls superstructure and roof beams of the electrostatic precipitator of boiler OP-110 No. 1

2014-03-26

Completion of assembly of collecting and discharge electrodes without final adjustment of the electrostatic precipitator of boiler OP-110 No. 1

2014-04-11

Completion of assembly of mechanical, electrical and Control and Measurement Instruments and Automation – notification of readiness for commissioning works of electrostatic precipitator of boiler OP-110 No. 1

2014-05-12

Finish of 72-hour test run for electrostatic precipitator of boiler OP-110 No. 1

2014-07-12

Gravitation tests of electrostatic precipitator of boiler OP-110 No. 1

2014-09-04

Hand-over to operation of the electrostatic precipitator OP-110 No. 1

2014-10-02

 

Electrostatic precipitator of boiler OP 110 No. 3

Delivery of the construction site

2014-07-21

Dismantling works of the electrostatic precipitator of steam boiler OP-110 No. 3

2014-08-22

Completion of assembly of walls superstructure and roof beams of the electrostatic precipitator of boiler OP-110 No. 3

2014-09-22

Completion of assembly of collecting and discharge electrodes without final adjustment of the electrostatic precipitator of boiler OP-110 No. 3

2014-10-08

Completion of assembly of mechanical, electrical and Control and Measurement Instruments and Automation – notification of readiness for commissioning works of electrostatic precipitator of boiler OP-110 No. 3

2014-10-30

Finish of 72-hour test run for electrostatic precipitator of boiler OP-110 No. 3

2014-11-12

Gravitation tests of electrostatic precipitator of boiler OP-110 No. 3

2015-02-02

Hand-over to operation of the electrostatic precipitator OP-110 No. 3

2015-03-11

 

Photos from the construction site